Amendments, Extensions and Corrections

Projects change. Your registration should keep up.

Extensions, plan and specification changes, change of promoter and corrections to MahaRERA registrations.

Who it applies to

Promoters whose completion date, plans, specifications, phasing, promoter entity or project details have changed or will change after registration.

ProvisionWhat it covers
Section 6Extension of registration for force majeure, on application in the prescribed form and fee; up to one year
Section 7(3)Authority may extend registration instead of revoking it, on terms it considers fit, in the interest of allottees
Rule 7, Maharashtra RERA Rules 2017Extension application in Form E; fee computed under Rule 7(3)
MahaRERA Orders 07/2019, 40/2022 and 40A/2023Section 7(3) extensions: consent of at least 51% of allottees in Format B, or a reasoned application with whatever consents are available, plus disclosure of pending complaints and litigation
Section 14(2)Additions or alterations to sanctioned plans or specifications need prior written consent of at least two-thirds of allottees, other than the promoter; minor additions or alterations permitted
Section 15Transfer of majority rights to a third party needs prior written consent of two-thirds of allottees and prior written approval of the Authority

Documents required

ChangeKey documents
Extension (Section 6 or 7(3))Form E, reasons for delay with evidence, revised schedule, Forms 1, 2 and 3 on current status, allottee consents in Format B, list of pending complaints and litigation
Plan or specification changeRevised sanctioned plans, architect's note on the change, allottee consents where Section 14(2) applies
Change of promoterTransfer agreement, allottee consents, KYC of incoming promoter, undertaking to honour existing agreements
CorrectionsSupporting document for each corrected field

Timeline

File extensions well before the registration validity expires; an application after expiry risks lapse and loss of portal services.

MahaRERA processing time depends on queries and, for Section 7(3), on its review of allottee interest.

Consequences of non-compliance

A lapsed registration stops sales and portal filings.

Plan changes without the required consent expose the promoter to complaints, rectification orders and refund with interest under Section 18.

An unapproved transfer of the project is a contravention attracting penalty under Section 61 of up to 5% of the estimated project cost.

How we help

  • Extension strategy: Section 6 or Section 7(3), with the evidence each needs
  • Allottee consent drives, Format B documentation and tracking
  • Revised Forms 1, 2 and 3 and an updated schedule that holds up to scrutiny
  • Plan change and Section 15 transfer applications
  • Corrections, phase changes, de-registration and revival of lapsed projects
  • Replies to MahaRERA notices and show-cause proceedings

Registration expiring in the next six months?

Request a consultation to plan the extension before the deadline.

Content as at 27-10-2026. General information only, not professional advice; see our Disclaimer.