Compliance Calendar
MahaRERA compliance calendar
Key recurring obligations for a MahaRERA-registered project, in financial-year order (April to March).
QPRs are due on 20 Jul, 20 Oct, 20 Jan and 20 Apr.
Fixed due dates every year
Quarterly progress reports are due within 20 days of each quarter end (MahaRERA Order No. 33/2022).
| Due | Obligation | Who certifies or files |
|---|---|---|
| 20 April | QPR for January to March | Promoter, with architect, engineer and CA certificates |
| 20 July | QPR for April to June | Promoter, with architect, engineer and CA certificates |
| 30 September | Form 5 annual report on statement of accounts (within six months of FY end) | Promoter's statutory auditor |
| 20 October | QPR for July to September | Promoter, with architect, engineer and CA certificates |
| 20 January | QPR for October to December | Promoter, with architect, engineer and CA certificates |
Event-based obligations
| When | Obligation | Who certifies or files |
|---|---|---|
| Before each withdrawal | Form 3 for withdrawal from the separate account (with Forms 1 and 2) | Practising CA other than the statutory auditor |
| Well before validity expires | Extension of registration | Promoter |
| Period under local law; where none, three months from OC | Conveyance to allottees or their association (Section 17) | Promoter |
| At least 60 days before the five-year validity ends | Agent registration renewal | Agent |
Related services
Quarterly Progress Reports →Form 3 and Form 5 →Extensions →Want us to track these for your projects?
Every project we handle goes on our compliance calendar, with reminders well before each due date.
Request a ConsultationContent as at 27-10-2026. Dates follow current MahaRERA directions and can change; see our Disclaimer.